Storm Bert expected this weekend

Self Authorisation

Self authorisation

Are you interested in authorising your own staff for Low Voltage (LV) or High Voltage (HV) connections?

This option for authorisation aligns with option one: section 5.2 in the Code of Practice. To self-authorise your staff you will need to accept all of the following responsibilities:

  • all work will be completed under your own safety rules and safety management systems
  • you and your staff must have some awareness of the local power network
  • you must take responsibility for testing and energisation during the works
  • you will need to complete an indemnity form to confirm you understand and accept these responsibilities
  • you will also need to attend a meeting with members of our system operation's and training academy teams. Please email us to arrange this meeting for a mutually convenient time.

HV only

Should you choose to self authorise HV connections (including option three: section 5.2 in the Code of Practice), there are some additional points you must discuss with us:

  • which party will be responsible for moving open points (Electricity North West or an Electricity North West authorised Independent Connections Provider)
  • if any test bushings or earthing harnesses are required for the work, we will provide the required equipment requested as long as you notify us in advance of the start date
  • the method of phasing out which must be determined prior to start date
  • time spent on site. There is a 12 hour time limit on the transfer of control; please be mindful of this when planning in any works
  • emergency return to service arrangements, as these will be required.

For more information please see our self-authorisation guide.