Self-determination of PoC

Self-determination of Point of Connection (PoC)

As a National Electricity Registered Scheme (NERS) accredited Independent Connection Provider (ICP) you can determine Points of Connection (PoC) for your customers.

This process gives you more freedom to determine how you wish to proceed with a connection. To self-determine your own PoC in our area you will need to request access to our network information and policy library. 

Once you have registered your PoC enquiry with us, you can choose whether to complete a network study yourself independently of us, or you can request us to complete this on your behalf. 

         

 If your point of connection is over a certain threshold we may check the connection to avoid any adverse impact on the network and other customers. We call this a 'network integrity check'

Check below to see if your connection requires a network integrity check.

Voltage

 

Type

 

Conditions for approval (network integrity check)

Extra High Voltage 33kV and 132kV   Demand, generation, or mixed   All submissions will be subject to a network integrity check
High Voltage   Demand, generation, or mixed   All submission >500kVA will be subject to a network integrity check
Low Voltage >100kVA   Demand, generation, or mixed   All submissions >100kVA will be subject to a network integrity check
Low Voltage <100kVA   Demand, generation, or mixed   No network integrity check required

Download our user guide

Find out how to get started and our process for self-determination of PoC.

Download

Contact us

If you have any specific questions about the process, get in touch with us.

Contact us

Notify us

Complete our notification form to let us know you wish to self-determine a Point of Connection (PoC).

Download

Adoption agreements

View and download our master adoption agreement and appendices.